time frame for building brick shed with a flat roof with an area if five square metres

How long does it take bricklayers to create a brick shed? I am looking for a brick shed with an area of five square metres to be assembled. I would like it to have a flat roof. How long could I expect professional contractors to take to put this together? Thanks!

Asked by Karen on 20th Aug 2020
Expert Trade Answers
"Approx 5-6 days. Depending on whether shed being built on slab or strip foundation."
Answered on 29th Oct 2020 - Member since Jun 2020 - report
"It should take a 2 and 1 approximately 4 days to build it"
Answered on 24th Aug 2024 - Member since Feb 2021 - report
"it should take about 5 days. it depends on specs of the building and roof. you have to take in drying times of materials."
Answered on 20th Aug 2020 - Member since Jun 2020 - report
"I would expect 2 men and labourers would do the brick work in 3-4 days

Roof 2 days

And making good a day

Not inc loading mixing etc ground prep slab etc"
Answered on 20th Aug 2020 - Member since Mar 2020 - report
Find Tradespeople, compare up to 3 quotes!
It's FREE and there are no obligations
Ask a Trade
Got a question that only a tradesperson can answer? We have thousands of trades ready to answer any question you may have.
Ask your question
Ask a Trade

Are you looking for advice on a DIY project or have a question for our tradespeople?

We'll email your question to tradespeople who are skilled in your chosen category.

Your question will be made public - please do not include any personal details.

{{ first(ask.errors)[0] }}

By continuing you agree to the Community Guidelines.

Report Content

{{ first(reportForm.errors) }}

Thank you

Your report has been created and will be investigated shortly.

Ready to get a price for your home improvement project?
Get started

Over 1 million homeowners and over 50,000 tradespeople
use MyJobQuote nationwide each year